Walker Street Upgrade, North Sydney CBD

Client: North Sydney Council
Location: North Sydney CBD
Date Completed: November 2015

Statewide Civil is proud to have been awarded its first project for North Sydney Council. Works included an upgrade of the existing drainage system, the installation of granite kerb & paved footpath.

The Walker St Upgrade project commenced in January 2015, with the installation of the new drainage line completed initially. With the need for rock excavation to achieve invert levels, the process was slower than anticipated. However, with some additional working shifts organised, the project was able to get back on track. With various challenges relating to pedestrian & vehicular traffic, as well as the commitment to local businesses, paving & kerb works were completed during both day & night in an attempt to minimise the disruption.